Commercial construction / interior fitout / NSW

One contractor from excavation to handover. Nowhere on your program does responsibility change hands.

Earthworks, structure and interior fitout, delivered by one company on one program and tracked in Procore.

Industrial and logistics. Commercial and retail. Fuel. Government and community. Institutional.

Two directors with 35 years each in the industry and over $100 million delivered between them, including single projects to $12 million.

Request early contractor involvement

Send the drawings. A director prices it and tells you what the site will actually cost to build, before your tender goes out.

35+Years each in the industry
$100M+Delivered between them
$12MSingle projects to
Aerial view of a completed commercial precinct at Hoxton Park
ExcavationStructureInterior fitoutHandover

02 / Package interfaces

Your program does not break inside a package. It breaks between them.

Earthworks, structure and interior fitout are usually three contracts, often tendered months apart. Each package carries its own program, its own float and its own defect liability period. Nobody carries the join between them.

Where it costs you

01Earthworks

Excavators and surveyors working across a large excavation site

Slab tolerance signed off to a structural spec, then racking or equipment arrives to a tighter one.

02Structure

Aerial view of a steel-framed community building under construction

Services penetrations set before the fitout scope was awarded, and cut again afterward.

03Interior fitout

Completed interior with timber floor, exposed steel and suspended lighting

A structural certificate outstanding while the certifier holds your Occupation Certificate.

In every one of those, two contractors have a defensible position and nobody owns the outcome. Your project manager sorts it out, and that was never priced into the job.

Three contracts is not just risk. It is slower.

Three tenders. Three sets of drawings issued and reissued. Three payment schedules, three variation registers and three defects lists. Three programs someone has to reconcile, and that someone works for you.

  • 03Tenders
  • 03Sets of drawings
  • 03Payment schedules
  • 03Variation registers
  • 03Defects lists
01

One contract

One contract removes all of it. Decisions get made in one meeting. Sequencing happens inside the company rather than between companies. When something changes, one contractor adjusts the whole run instead of three renegotiating with each other.

Faster, better coordinated, and you always know who to call.

03 / One entity / whole run

The company was formed to hold the whole run, not one package of it.

MKP Projects builds structure and civil, with its own plant for earthworks and excavation. Building Project Solutions builds commercial interiors.

They did not agree to work together on projects. They formed one company.

One entity.
Both directors in it.
Earthworks through to handover inside it.

01 / Excavate

Excavate

Aerial view of excavation works beside sporting fields

02 / Build

Build

Steel roof framing being installed inside a community sports building

03 / Fit out

Fit out

Finished upper-level interior with timber floor and exposed steel beams

04 / Hand over

Hand over

Aerial view of the completed sports facility and surrounding grounds
01

Excavate, build, fit out, hand over

We start on the dirt with our own plant and finish with the certificates in your hand.

The plant is ours. Earthworks are self-performed, so your start date does not sit behind a hired machine or somebody else's job.

Nothing gets retendered halfway through. Nothing waits for the next contractor to be appointed. The people who set the slab levels are the people installing against them nine months later, which is the entire reason those two things end up matching.

02

One program, in Procore, with your login

The same system your project manager already works in.

Program, progress, RFIs, variations and documents in one place across the whole run. You are not chasing three contractors for three status updates, and you are not finding out at the site meeting.

03

We price it before the tender goes out

Early contractor involvement. Send us the drawings and you get a cost plan against the current design, a buildability review naming what will cost you money to build, an outline program with the long lead items identified, and where the design can be changed to take cost out.

Before you commit. Not as a variation afterward.

04

And one defect liability period across the whole run.

04 / Delivery record

The entity is new. The record behind it is not.

BPS Constructions Aus was formed in 2026, on purpose, so one company could hold a project from excavation to handover.

The delivery record belongs to the two companies inside it, and to two directors with 35 years each in the industry and over $100 million delivered between them.

Structure and civil: MKP Projects

Early contractor involvement, design and construct, construct only, civil and earthmoving. Plant owned rather than hired.

Delivered, by sector:

Completed multi-level aged care facility with accessible terraces

Institutional.

Southhaven Aged Care, Padstow Heights.

$7 million, for Christadelphian Aged Care.

View case study
Completed Glen Alpine Golf Club amenities building beside bushland

Government and community.

Glen Alpine Golf Club amenities.

$1.3 million, for Campbelltown City Council, 2024.

View case study
Completed Berala Community Centre

Government and community.

Berala Community Centre

Client: Auburn City Council
Value: $2m

View case study
35+Years each in the industry
$100M+Delivered between them
$12MSingle projects to

Interior fitout: Building Project Solutions

Commercial interiors across retail, hospitality, medical and clinical, and gyms. Greater Sydney, plus multi-site rollouts for operators running more than one site.

Every variation raised in writing with cost and time impact, and approved before the work goes ahead. That is how the company has run from the start, not a policy written for this page.

Systems and reporting

Procore across the whole run. Program, progress, RFIs, variations and documents in one place, with your own login.

If your project manager wants to know where something is at four in the afternoon, he looks. He does not ring three contractors.

Director oversight on every project

Both directors oversee every job the company runs, from tender through to handover.

Not a principal at the tender and a coordinator afterward.

05 / From ECI to handover

Six stages, one contractor, no retendering in the middle

01Before you commit
02Award and mobilisation
03Earthworks
04Structure
05Interior fitout
06Handover
01

Before you commit

Early contractor involvement on your drawings. Cost plan, buildability review, outline program with long lead items, and where the design can be changed to take cost out.

02

Award and mobilisation

One contract covering the full run. Procore access live from day one.

The program you are given at award is the program the site works to, with the fitout sequence already written into it.

03

Earthworks

Self-performed. Bulk and detail excavation, and the site set up for the structure going on it.

Latent conditions get reported the day they are found, priced, and brought to you before anything proceeds.

04

Structure

Progress, RFIs, variations and inspection records go into Procore as they happen.

You get a program and progress report on a fixed cycle, not when you chase one.

05

Interior fitout

No retender. No new contractor learning the site. The fitout was sequenced alongside the structure, by the people who built it.

06

Handover

Certificates, warranties, manuals and as-builts as one complete pack, issued at practical completion rather than negotiated afterward.

Then one defect liability period covering the whole run.

06 / Defect liability

One defect liability period across the whole run

Tender earthworks, structure and fitout as separate packages, which is how most of these projects get procured, and you end up with three defect liability periods.

The earthworks period started when their package finished, probably a year before anyone else's. The structural period started at their practical completion. The fitout period started at yours.

Three start dates, three expiry dates, three companies. When something fails where two packages meet, at least two of them tell you it is not their scope, and both are right.

Earthworks period

Structural period

Fitout period

One period, one start date, one contractor

Ours is one period, one start date, one contractor

It begins at practical completion of the whole project and it covers the run. Excavation, structure, interior fitout.

You do not diagnose the cause before you can make the claim.

You report it, and working out which trade it came from is our problem, not yours.

The limits, on the page

A guarantee you have to read twice is not a guarantee, so here they are.

Twelve months from practical completion.

One defined period, not a promise to look after you.

The remedy is rectification.

We come back and fix it. It does not extend to consequential loss.

It covers our work.

Not client-supplied items, not contractors you engage direct, not design by others where the project is not design and construct, not fair wear, not damage from misuse or alteration after handover.

Written notice inside the period, and site access to do the work.

Every one of those is about what caused the defect. None of them change who you call.

Why this is worth saying out loud

We audited the New South Wales contractors delivering structure and interior fitout together. Every one sells a single point of accountability.

None of them will carry one defect liability period across both scopes, because their two scopes sit in two companies. Ours do not.

07 / Pre-tender ECI

Send us the drawings before the tender goes out

Early contractor involvement happens while you can still change something. Send the drawings before the tender goes out and you get four things back.

01

A cost plan against the current design.

What the project actually builds for, not a rate per square metre.

02

A buildability review.

Where the drawings will cost you money on site, and what will be found once the excavator starts.

03

An outline program.

Full run, excavation to handover, with the long lead items identified.

04

Where cost can come out.

Design changes that reduce the number without reducing what you are getting.

It is yours either way

The cost plan, the program and the buildability review are yours whether you appoint us or not.

If the project has to go to open tender, take them with you.

We would rather be the contractor who found the problem in the drawings than the one who priced around it.

Who you deal with

A director. On the drawings, not on a discovery call.

If we are not the right contractor for the project we will tell you early, and what we have given you still works with whoever you appoint.

Early contractor involvement

Send us the drawings before the tender goes out

Send the drawings and the site address. If you would rather start with a capability statement for your procurement file, ask for that instead and we will send it the same way.

Insurances, systems and referees are in the capability statement. Ask and it comes back the same day.

08 / Procurement timing

The decision that closes this off gets made before the tender

Most of what a project costs is decided in the drawings, not on the site.

By the time documentation is complete and the packages are split, the expensive decisions are made. What is left is choosing who executes them.

Earlier is not a discount. It is more room.

01

Bring us in at design and the buildability problems get drawn out rather than priced in.

02

Bring us in at procurement strategy and the run stays in one contract.

03

Bring us in after award and we work inside decisions someone else made, on a program with no float left.

Once the packages are separated, one contract across the run is gone

Not because we would not do it. Because the sequencing already belongs to someone else, and the fitout gets tendered months after the structure is underway.

That is the day the join between packages becomes yours to manage again.

If the strategy is already set

Plenty of projects are past that point, or run to a procurement policy that was never yours to change.

We tender packages too. Structure on its own, fitout on its own, or both under a head contract where the client wants them separated on paper.

The whole run is what we are built for. It is not the only way we work.

09 / Due diligence

On the entity being new

We have said it on this page rather than leaving you to find it.

It is new because two builders with 35 years each decided a project should not change hands three times between the first excavation and handover. That decision is the company. Everything else here follows from it.

Before you shortlist

Ask every contractor on your list who carries the defect liability period across structure and interior fitout.

Not who is accountable. Who carries the period.

Most will answer the first question, because they cannot answer the second.

Send us the drawings before the tender goes out.